James Szafarczyk
Gerald Penkszik
Samuel Dropchuk
Julius Kulchesky
Chester Hall
Russel Kraft

Edward J. Sawtell
John M. Griffin
Edward J. Sawtell
Henry P. Gelinski
Walter J. Krzyzoston
Frank C. Long
Martin Bishop

 



 

 


Fire Log, 6 August 1984 (3001 Miller)
0714: First alarm: E 4; Quad 2; Rescue I
0721: Second alarm: HP engine
0723: Third alarm: Quad I
0745: Fourth alarm: Det. E 41, 39, 5; L 17; Squad 3
0759: Fifth alarm: Aerial I
  Special calls: Det. total: 25 eng 10 lad., 5 b.c., 6 sq.
1801: Under control
Raging Hamtramck Fire - Continued
by Harvey Eisner

Hamtramck Chief Sam Dropchuk, a 17-vear veteran and chief for the last four years, arrived on the scene shortly after Detroit firefighters. "On arrival we had total involvement of the second floor in the rear, and shortly thereafter it went through the roof," says Dropchuk. "The building was sprinklered but there was some concern about whether the sprinkler system was turned on in that portion of the building." Adds he: "It was totally out of hand when we arrived."

Firefighters reported hearing water motor gongs, and, as far as officials can ascertain, the sprinkler system was working. Notes Dropchuk: "When we arrived the fire was beyond control of the I sprinklers; too many heads had popped to contain the fire."

Detroit was setting up an aerial ladder and Hamtramck's ladder truck was ordered to position in the rear of the complex on a set of railroad tracks. "There was a 6-inch main on Miller," says Dropchuk. "It was very small and very old, and we had so many pumpers." To the east of the complex was an empty lot where the Champion Sparkplug Company had been located. Several yard hydrants were shut off due to construction. Harntrarnck water officials were called to open the mains, and Detroit was asked to open nearby gates to increase pressure in the area.

Firefighters tried to make a stand several times, and at one point repositioned to an area between the two buildings. There was no fire showing. They were ordered to open up the building and set up for ladder pipe operations again. Detroit's boat tender arrived and laid a 5-inch line off a 24-inch main two blocks away. But according to Morris, "Before we got water, the fire was past us."

Recalls Detroit's Chief of Department Elmer Chapman: "The fire was halfway through one section when I arrived. Due to the lack of water we weren't going to stop it. Some pumpers had very low pressure and others were drawing a vacuum."

At this point there were only two monitors with sufficient pressure to reach the building. The fire spread with lightning speed throughout the structure. "The floors were oil soaked, and the car storage didn't help either," explains Dropchuk. "A 100-gallon gasoline tank was also located inside the structure." Adding to the spread of fire were several holes in the floor where machinery had been removed.

Growing in intensity, the fire traveled to the brick passageway that linked the two structures. Intense radiated heat forced firefighters to retreat and reposition further down the street.

Explains Solomon: "It was tough to get close. Every time we*d set up, we d have to break down, move back and set up again. The times we did get close we didn't have adequate water pressure." The 5-inch, plastic-covered hose had to be abandoned. Says Morris: "It was too hot to get it so we had to leave 1500 feet of it." Loss of the hose cost Detroit $21,000.

Additional companies arrived from Detroit in rapid succession, including the city's two 100-foot aerial platforms. The units were ordered to pull back and protect adjoining buildings and the small factories across the street. "That's all we could do," explains Chief Chapman.

Says firefighter Morris: "When the fire started to create its own winds we knew we were in trouble. The roofs of several wood-frame dwellings down the street had caught fire." The command post had been located in front of the factories across the street from the fire building, but when the intense radiated heat developed, the command post was repositioned one block to the west. Fire had extended to several of the factories, and when companies could be freed up, they were used wherever possible.

Several hundred nearby residents were evacuated from the area to protect them from toxic fumes, possible explosions and flying shrapnel.

A gas main popped from the heat of the fire, creating more problems for firefighters. Intense heat also caused explosions in the gasoline tanks of cars stored in the building. As the fire spread through the complex it caused several major collapses, but these did not endanger firefighters. Explains Chief Dropchuk: "We didn't worry too much about collapse because the radiant heat was so great, we didn't get too close."

With adequate help, exposures protected and the fire dying out after the structures had collapsed and the combustibles were consumed, the fire was declared under con- trol at 6:01 P.M. Rail traffic behind the fire building was halted, and construction workers at the new General Motors Poletown Assembly plant a few blocks away were given the rest of the day off due to the noxious fumes which passed over the plant.

Four firefighters sustained minor injuries in the blaze. Due to the number of chemicals inside the complex, several firefighters from all three departments suffered rashes, sore throats, headaches and nausea.

"The first three days after the fire we reframed from putting out the last remnants while water samples were taken by environmental officials," says Chief Dropchuk. "After the third day they gave us the okay to extinguish the fires." The International Association of Firefighters sent a task force to test the firefighters for toxicity.

The entire Harntrarnck Fire Department responded to the blaze, along with 25 engines, 10 ladder companies, five battalion chiefs and six manpower squads from Detroit. Several units from Highland Park also operated at the fire.

Many firefighters on the scene were impressed by the magnitude of the fire. "It was amazing to see the fire spread. I've never seen anything like it," says Solomon. "Everytime we'd hook up we thought we could hold it, but we had to keep falling back." Adds Chief Chapman: "The fire was just awesome. We knew we could knock it down but we didn't have water. We couldn't even get a couple of streams. We felt helpless."

According to Dropchuk, "It was all the factors involved -rapid spread, feeding on such a large structure and water problems. We could have had another 100 firefighters at the scene, and they wouldn't have stopped it. It had so much wood and combustibles to feed on, and the sprinklers were nonfunctionable after the first 15 minutes. Everything played against us."

Damage was estimated at $2 million to the structure and $7 million to the contents. Over $8000 of Hamtramck equipment was lost or damaged

During the post-fire investigation, a 12-year-old boy was arrested and later confessed to starting a fire in the warehouse. Apparently, he was setting fire to paper airplanes when one ignited some combustible material. The fire burned for possibly up to an hour before being discovered by an employee arriving at the complex.

"With a building of this size and age, the size of our department and the low water pressure, I don't think it could have been stopped," states Chief Dropchuk. "They don't build buildings like this anymore, thank heavens! They are nightmares for fire departments."

after the fire, from aboveHamtramck firefighters have responded to fires at the old warehouse complex several times in the past few years. A year ago a fire there was extinguished by the plant's sprinkler system; several months ago, units were called when an ammonia tank ruptured, filling the structure with noxious fumes. Just two weeks before the August 6 blaze, a fire broke out in the building and was contained by the sprinkler system before firefighters arrived at the scene and extinguished it completely.

Detroit firefighters were also familiar with the site of the fire, having assisted Hamtramck on several occasions on mutual aid, though never at such a serious incident as the August 6 fire. The warehouse complex is only two blocks away from the site of numerous arson fires that struck the area in the last few years. After General Motors decided to locate its new assembly plant in this area, arson fires were fought night and day in buildings slated for demolition in the Poletown area.

click on pictures to expand



This article originally appeared in FIREHOUSE MAGAZINE November 1984.

Back to Part 1

 



 

09-18-03 Polish Market
12-30-98 Mother Wattles
08-06-84 Ida Windows
00-00-91 A&C
01-20-76 Polar Brand
00-00-68 Hamt. Lumber
00-00-33 Magnesium fire
12-16-19

 

// home // community // events // history // apparatus // pictures // meet // newslinks // st. florian // guestbook // help //

Hamtramck Firefighters Association
P.O. Box 133
Hamtramck, MI 48212

e-mail / about this site
Site designed & Maintained by
John Dropchuk